Action Date | Action Description |
---|---|
Apr 07, 2006 | Maintenance Certification Request |
Apr 10, 2006 | Administrative Review for Completeness |
May 31, 2006 | Team Review for Completeness |
May 31, 2006 | Application Accepted |
Jun 02, 2006 | Engineering Report |
Jun 02, 2006 | Typist for Processing |
Jun 02, 2006 | Executive Sign Off |
Jun 02, 2006 | Sent to Photo Copy |
Jun 02, 2006 | Permit Approved |