Action Date | Action Description |
---|---|
Apr 12, 2006 | Assent Application Received |
Apr 14, 2006 | Administrative Review for Completeness |
Apr 21, 2006 | Team Review for Completeness |
Apr 21, 2006 | Application Accepted |
Aug 03, 2006 | HPHC Historical Preservation Comments/Concerns |
Aug 03, 2006 | HPHC Historical Preservation No Effect |
Aug 08, 2006 | Typist for Processing |
Aug 08, 2006 | Biologist Report |
Aug 08, 2006 | Sent to Photo Copy |
Aug 08, 2006 | Permit Approved |
Aug 09, 2006 | Executive Sign Off |
Aug 15, 2006 | Land Evidence Date |
Jan 16, 2008 | Modification Request |
Jan 17, 2008 | Administrative Review for Completeness |
Mar 07, 2008 | Team Review for Completeness |
Apr 14, 2008 | Biologist Report |
Apr 14, 2008 | Typist for Processing |
Apr 14, 2008 | Executive Sign Off |
Apr 14, 2008 | Sent to Photo Copy |
Apr 14, 2008 | Modification Approved |
Apr 22, 2008 | Land Evidence Date |