Action Date | Action Description |
---|---|
Apr 25, 2006 | Assent Application Received |
Apr 26, 2006 | Administrative Review for Completeness |
May 01, 2006 | Team Review for Completeness |
May 01, 2006 | Application Accepted |
May 17, 2006 | HPHC Historical Preservation No Effect |
May 19, 2006 | Biologist Report |
May 19, 2006 | Engineering Report |
May 22, 2006 | Typist for Processing |
May 22, 2006 | Executive Sign Off |
May 22, 2006 | Sent to Photo Copy |
May 22, 2006 | Permit Approved |
Aug 28, 2006 | Land Evidence Date |