Action Date | Action Description |
---|---|
Dec 22, 2006 | Assent Application Received |
Dec 28, 2006 | Administrative Review for Completeness |
Jan 19, 2007 | Deficient Application - Owner Notification Sent |
Apr 16, 2007 | Deficient Application Picked Up |
May 09, 2007 | Deficiency Response Received |
Jun 26, 2007 | Team Review for Completeness |
Jun 26, 2007 | Team Review for Completeness |
Jun 26, 2007 | Application Accepted |
Jun 26, 2007 | Category A* (Docks) |
Jul 16, 2007 | HPHC Historical Preservation No Effect |
Jul 23, 2007 | Plans Received |
Aug 09, 2007 | Plans Received |
Aug 16, 2007 | 30 day Public Notice Issued |
Sep 13, 2007 | Dock Meeting Scheduled (Admin) |
Sep 13, 2007 | Dock Meeting -- To Council |
Sep 16, 2007 | Public Notice End Date |
Sep 24, 2007 | US Army Corp of Engineers Permit Date |
Sep 27, 2007 | US Army Corps of Engineers Approval Received |
Oct 31, 2007 | Engineering Report |
Nov 30, 2007 | Biologist Report |
Dec 05, 2007 | Supervisor Biologist SignOff |
Dec 05, 2007 | Supervisor Engineer SignOff |
Dec 05, 2007 | Executive Signoff of Staff Reports |
Jan 23, 2008 | Ready to Schedule Semi-Monthly Meeting |
Feb 19, 2008 | Mail Agenda Notice |
Feb 26, 2008 | Council Approval Granted |
Feb 26, 2008 | Semi-Monthly Meeting Date Scheduled |
Mar 05, 2008 | Typist for Processing |
Mar 05, 2008 | Executive Sign Off |
Mar 05, 2008 | Sent to Photo Copy |
Mar 05, 2008 | Permit Approved |
Mar 06, 2008 | Stipulation Package by Engineer |
Mar 10, 2008 | Land Evidence Date |
Oct 06, 2008 | Legal Response/Decision |