Action Date | Action Description |
---|---|
Jul 17, 2008 | Assent Application Received |
Jul 18, 2008 | Administrative Review for Completeness |
Jul 22, 2008 | Team Review for Completeness |
Jul 29, 2008 | Application Accepted |
Jul 29, 2008 | Team Review for Completeness |
Jul 30, 2008 | Category A* (Docks) |
Aug 01, 2008 | HPHC Historical Preservation No Effect |
Sep 02, 2008 | 30 day Public Notice Issued |
Oct 01, 2008 | Public Notice End Date |
Oct 14, 2008 | US Army Corp of Engineers Permit Date |
Oct 14, 2008 | US Army Corps of Engineers Approval Received |
Nov 05, 2008 | Typist for Processing |
Nov 05, 2008 | Executive Sign Off |
Nov 05, 2008 | Sent to Photo Copy |
Nov 05, 2008 | Permit Approved |
Nov 05, 2008 | Biologist Report |
Nov 05, 2008 | Engineering Report |
Feb 23, 2009 | Land Evidence Date |