Action Date | Action Description |
---|---|
Jul 01, 2009 | Team Review for Completeness |
Jul 01, 2009 | Assent Application Received |
Jul 01, 2009 | Administrative Review for Completeness |
Jul 02, 2009 | Team Review for Completeness |
Jul 02, 2009 | Application Accepted |
Jul 21, 2009 | Biologist Report |
Jul 21, 2009 | Engineering Report |
Jul 22, 2009 | Typist for Processing |
Jul 22, 2009 | Executive Sign Off |
Jul 22, 2009 | Permit Approved |
Jul 24, 2009 | Sent to Photo Copy |
Aug 27, 2009 | HPHC Historical Preservation No Effect |
Sep 24, 2009 | Land Evidence Date |
Jul 03, 2012 | Extension of Permit Request |
Jul 03, 2012 | Extension Toll letter mailed |
Apr 30, 2013 | Modification Request |
May 01, 2013 | Administrative Review for Completeness |
May 03, 2013 | Plans Received |
May 06, 2013 | Team Review for Completeness |
May 08, 2013 | Biologist Report |
May 10, 2013 | Modification Approved |
May 13, 2013 | Executive Sign Off |
May 13, 2013 | Sent to Photo Copy |
Jun 10, 2013 | Typist for Processing |
Jun 10, 2013 | HPHC Historical Preservation No Effect |
Sep 10, 2013 | Phone Call |
Sep 24, 2013 | Duplicate Original Assent requested/mailed |
Oct 16, 2013 | Land Evidence Date |
Mar 20, 2014 | Modification Request |
Mar 21, 2014 | Administrative Review for Completeness |
Mar 21, 2014 | Team Review for Completeness |
Mar 31, 2014 | Biologist Report |
Apr 07, 2014 | Typist for Processing |
Apr 07, 2014 | Modification Approved |
Apr 09, 2014 | Executive Sign Off |
Apr 09, 2014 | Sent to Photo Copy |
Apr 15, 2014 | Land Evidence Date |
Apr 23, 2014 | HPHC Historical Preservation No Effect |