Action Date | Action Description |
---|---|
May 12, 2011 | Assent Application Received |
May 13, 2011 | Administrative Review for Completeness |
Jun 24, 2011 | Team Review for Completeness |
Jun 24, 2011 | Team Review for Completeness |
Jun 24, 2011 | Application Accepted |
Aug 26, 2011 | Additional Information Requested from Applicant |
Aug 30, 2011 | Certified Receipt Received |
Sep 22, 2011 | Plans Received |
Oct 04, 2011 | Biologist Report |
Oct 04, 2011 | Engineering Report |
Oct 05, 2011 | Typist for Processing |
Oct 05, 2011 | Permit Approved |
Oct 06, 2011 | Executive Sign Off |
Oct 06, 2011 | Sent to Photo Copy |
Oct 25, 2011 | Land Evidence Date |
Oct 25, 2011 | Commencement of Work Notice received |