Action Date | Action Description |
---|---|
Sep 12, 2011 | Assent Application Received |
Sep 12, 2011 | Administrative Review for Completeness |
Sep 19, 2011 | Team Review for Completeness |
Sep 19, 2011 | Application Accepted |
Sep 22, 2011 | Engineering Report |
Sep 29, 2011 | Typist for Processing |
Sep 29, 2011 | Executive Sign Off |
Sep 29, 2011 | Permit Approved |
Sep 30, 2011 | Sent to Photo Copy |
Oct 18, 2011 | HPHC Historical Preservation No Effect |
Dec 01, 2011 | Modification Request |
Dec 02, 2011 | Administrative Review for Completeness |
Dec 02, 2011 | Team Review for Completeness |
Dec 09, 2011 | Typist for Processing |
Dec 09, 2011 | Modification Approved |
Dec 12, 2011 | Executive Sign Off |
Dec 12, 2011 | Sent to Photo Copy |