Action Date | Action Description |
---|---|
Oct 06, 2011 | Assent Application Received |
Oct 07, 2011 | Administrative Review for Completeness |
Oct 11, 2011 | Team Review for Completeness |
Oct 11, 2011 | Team Review for Completeness |
Oct 11, 2011 | Application Accepted |
Oct 13, 2011 | 30 day Public Notice Issued |
Oct 18, 2011 | HPHC Historical Preservation No Effect |
Nov 13, 2011 | Public Notice End Date |
Jan 05, 2012 | Biologist Report |
Jan 05, 2012 | Engineering Report |
Jan 06, 2012 | Supervisor Biologist SignOff |
Jan 06, 2012 | Supervisor Engineer SignOff |
Jan 06, 2012 | Executive Signoff of Staff Reports |
Jan 30, 2012 | Objections/Comments Received |
Feb 03, 2012 | Entry of Appearance Received |
Feb 16, 2012 | Ready to Schedule Semi-Monthly Meeting |
Feb 16, 2012 | Mail Agenda Notice |
Feb 28, 2012 | Council Approval Granted |
Feb 28, 2012 | Semi-Monthly Meeting Held |
Feb 28, 2012 | Semi-Monthly Meeting Date Scheduled |
Mar 09, 2012 | Water Quality Certification |
Mar 12, 2012 | Stipulation Package from Biologist |
Mar 12, 2012 | Stipulation Package by Engineer |
May 18, 2012 | Legal Response/Decision |
Jun 19, 2012 | Typist for Processing |
Jun 19, 2012 | Permit Approved |
Jun 20, 2012 | Executive Sign Off |
Jun 20, 2012 | Sent to Photo Copy |
Jun 25, 2012 | Land Evidence Date |
Jul 26, 2012 | Water Quality Certification |