Action Date | Action Description |
---|---|
Monitoring Report | |
Dec 27, 2011 | Assent Application Received |
Dec 29, 2011 | Administrative Review for Completeness |
Jan 09, 2012 | Team Review for Completeness |
Jan 09, 2012 | Team Review for Completeness |
Jan 09, 2012 | Application Accepted |
Jan 14, 2012 | HPHC Historical Preservation No Effect |
Jan 30, 2012 | Additional Information Requested from Applicant |
Mar 30, 2012 | 30-Day Notification of Cancellation letter |
Apr 04, 2012 | Certified Receipt Received |
Apr 27, 2012 | Plans Received |
May 08, 2012 | 30-Day Notification of Cancellation letter |
Jun 04, 2012 | Additional Information Received |
Jun 14, 2012 | Engineering Report |
Jun 14, 2012 | Biologist Report |
Jun 15, 2012 | Permit Approved |
Jun 15, 2012 | Typist for Processing |
Jun 18, 2012 | Executive Sign Off |
Jun 18, 2012 | Sent to Photo Copy |
Jul 02, 2012 | Land Evidence Date |
May 04, 2018 | Additional Information Requested from Applicant |
May 14, 2018 | Monitoring Report |