Action Date | Action Description |
---|---|
Jan 13, 2012 | Assent Application Received |
Jan 16, 2012 | Administrative Review for Completeness |
Jan 16, 2012 | Team Review for Completeness |
Jan 16, 2012 | Application Accepted |
Feb 08, 2012 | HPHC Historical Preservation No Effect |
Feb 13, 2012 | Permit Approved |
Feb 13, 2012 | Biologist Report |
Feb 13, 2012 | Typist for Processing |
Feb 14, 2012 | Executive Sign Off |
Feb 14, 2012 | Sent to Photo Copy |
Feb 16, 2012 | Land Evidence Date |