Action Date | Action Description |
---|---|
Jan 30, 2012 | Assent Application Received |
Jan 30, 2012 | Administrative Review for Completeness |
Jan 31, 2012 | Team Review for Completeness |
Jan 31, 2012 | Team Review for Completeness |
Jan 31, 2012 | Application Accepted |
Feb 08, 2012 | 30 day Public Notice Issued |
Mar 06, 2012 | HPHC Historical Preservation No Effect |
Mar 09, 2012 | Public Notice End Date |
Jun 27, 2012 | 30 day Public Notice Issued |
Jul 27, 2012 | Public Notice End Date |
Aug 01, 2012 | Additional Information Received |
Aug 02, 2012 | US Army Corps of Engineers Approval Received |
Aug 23, 2012 | Biologist Report |
Aug 23, 2012 | Engineering Report |
Aug 30, 2012 | Permit Approved |
Aug 30, 2012 | Typist for Processing |
Sep 04, 2012 | Executive Sign Off |
Sep 04, 2012 | Sent to Photo Copy |
Sep 28, 2012 | Land Evidence Date |