Action Date | Action Description |
---|---|
Feb 14, 2012 | Assent Application Received |
Feb 14, 2012 | Administrative Review for Completeness |
Feb 16, 2012 | Team Review for Completeness |
Feb 16, 2012 | Team Review for Completeness |
Feb 16, 2012 | Application Accepted |
Feb 28, 2012 | HPHC Historical Preservation No Effect |
Mar 06, 2012 | 30 day Public Notice Issued |
Apr 06, 2012 | Public Notice End Date |
May 15, 2012 | Additional Information Received |
Jul 09, 2012 | Additional Information Received |
Jul 23, 2012 | US Army Corps of Engineers Approval Received |
Jul 31, 2012 | Category A* (Docks) |
Jul 31, 2012 | Biologist Report |
Jul 31, 2012 | Engineering Report |
Aug 01, 2012 | Permit Approved |
Aug 01, 2012 | Typist for Processing |
Aug 02, 2012 | Executive Sign Off |
Aug 02, 2012 | Sent to Photo Copy |
Aug 03, 2012 | Land Evidence Date |