Action Date | Action Description |
---|---|
Sep 10, 2012 | Assent Application Received |
Sep 11, 2012 | Administrative Review for Completeness |
Sep 11, 2012 | Team Review for Completeness |
Sep 11, 2012 | Team Review for Completeness |
Sep 12, 2012 | Deficient Application - Owner Notification Sent |
May 20, 2013 | Deficiency Response Received |
Jun 05, 2013 | Team Review for Completeness |
Jun 05, 2013 | Team Review for Completeness |
Jun 05, 2013 | Deficient Application - Owner Notification Sent |
Jun 21, 2013 | Application Accepted |
Jun 21, 2013 | Finding of No Significant Impact-OTC |
Oct 15, 2015 | Letter of Authorization |