Action Date | Action Description |
---|---|
Oct 03, 2012 | Assent Application Received |
Oct 03, 2012 | Administrative Review for Completeness |
Oct 11, 2012 | Team Review for Completeness |
Oct 11, 2012 | Team Review for Completeness |
Oct 11, 2012 | Application Accepted |
Oct 25, 2012 | HPHC Historical Preservation No Effect |
Oct 31, 2012 | Additional Information Received |
Nov 26, 2012 | 30 day Public Notice Issued |
Dec 26, 2012 | Public Notice End Date |
Feb 06, 2013 | Plans Received |
Feb 25, 2013 | US Army Corp of Engineers Permit Date |
Feb 27, 2013 | Plans Received |
Mar 21, 2013 | Additional Information Received |
Mar 26, 2013 | Category A* (Docks) |
Mar 26, 2013 | Typist for Processing |
Mar 26, 2013 | Biologist Report |
Mar 26, 2013 | Engineering Report |
Mar 27, 2013 | Executive Sign Off |
Mar 27, 2013 | Sent to Photo Copy |
Mar 27, 2013 | Permit Approved |
Apr 05, 2013 | Land Evidence Date |