Action Date | Action Description |
---|---|
Mar 06, 2013 | Maintenance Certification Request |
Mar 06, 2013 | Administrative Review for Completeness |
Mar 07, 2013 | Application Accepted |
Mar 08, 2013 | Team Review for Completeness |
Mar 12, 2013 | Team Review for Completeness |
Mar 14, 2013 | Typist for Processing |
Mar 14, 2013 | Executive Sign Off |
Mar 14, 2013 | Sent to Photo Copy |
Mar 25, 2013 | Assent Correction Mailed |
Mar 25, 2013 | Permit Approved |
Mar 27, 2013 | Land Evidence Date |
Jun 26, 2013 | Duplicate Original Assent requested/mailed |
Jul 09, 2013 | Land Evidence Date |
Aug 08, 2013 | Extension of Permit Request |