Action Date | Action Description |
---|---|
Mar 15, 2013 | Assent Application Received |
Mar 18, 2013 | Administrative Review for Completeness |
Mar 20, 2013 | Team Review for Completeness |
Mar 20, 2013 | Team Review for Completeness |
Mar 20, 2013 | Application Accepted |
May 06, 2013 | HPHC Historical Preservation No Effect |
Jun 10, 2013 | Plans Received |
Jun 13, 2013 | Additional Information Received |
Jun 19, 2013 | Engineering Report |
Jun 20, 2013 | Biologist Report |
Jun 21, 2013 | Typist for Processing |
Jun 21, 2013 | Permit Approved |
Jun 25, 2013 | Executive Sign Off |
Jun 25, 2013 | Sent to Photo Copy |
Aug 07, 2013 | Land Evidence Date |
Mar 28, 2014 | Modification Request |
Mar 31, 2014 | Administrative Review for Completeness |
Apr 01, 2014 | Team Review for Completeness |
Apr 28, 2014 | HPHC Historical Preservation No Effect |
Apr 29, 2014 | Modification Approved |
Apr 29, 2014 | Biologist Report |
May 15, 2014 | Assent Correction Request Received |
May 27, 2014 | Land Evidence Date |
Mar 18, 2015 | Modification Request |
Mar 19, 2015 | Administrative Review for Completeness |
Mar 19, 2015 | Team Review for Completeness |
Mar 19, 2015 | Team Review for Completeness |
Apr 24, 2015 | Plans Received |
May 04, 2015 | Biologist Report |
May 04, 2015 | Engineering Report |
May 08, 2015 | Typist for Processing |
May 18, 2015 | Executive Sign Off |
May 18, 2015 | Sent to Photo Copy |
Aug 13, 2015 | Land Evidence Date |