Action Date | Action Description |
---|---|
Apr 05, 2013 | Buffer Zone Management Application Received |
Apr 07, 2013 | Administrative Review for Completeness |
Apr 09, 2013 | Team Review for Completeness |
Apr 09, 2013 | Team Review for Completeness |
Apr 09, 2013 | Application Accepted |
Apr 19, 2013 | HPHC Historical Preservation No Effect |
May 10, 2013 | Biologist Report |
May 10, 2013 | Engineering Report |
May 16, 2013 | Typist for Processing |
May 16, 2013 | Permit Approved |
May 21, 2013 | Executive Sign Off |
May 21, 2013 | Sent to Photo Copy |
Jun 03, 2013 | Land Evidence Date |
Feb 08, 2016 | Monitoring Report |
Feb 17, 2016 | Plans Received |
May 24, 2016 | Letter of Authorization |
Dec 12, 2016 | Correspondence Received |