Action Date | Action Description |
---|---|
May 28, 2013 | Assent Application Received |
May 29, 2013 | Administrative Review for Completeness |
May 30, 2013 | Team Review for Completeness |
May 30, 2013 | Team Review for Completeness |
May 30, 2013 | Application Accepted |
Jun 11, 2013 | Biologist Report |
Jun 11, 2013 | Engineering Report |
Jun 12, 2013 | Typist for Processing |
Jun 12, 2013 | Permit Approved |
Jun 14, 2013 | Executive Sign Off |
Jun 14, 2013 | Sent to Photo Copy |
Jun 20, 2013 | Land Evidence Date |
Jul 09, 2013 | HPHC Historical Preservation No Effect |