Action Date |
Action Description |
Dec 04, 2014 |
Assent Application Received |
Dec 12, 2014 |
Team Review for Completeness |
Dec 12, 2014 |
Application Accepted |
Dec 12, 2014 |
HPHC Historical Preservation No Effect |
Dec 12, 2014 |
Category B assigned |
Jan 12, 2015 |
30 day Public Notice Issued |
Jan 23, 2015 |
Correspondence Received |
Feb 12, 2015 |
Public Notice End Date |
Feb 27, 2015 |
Objections/Comments Received |
Mar 02, 2015 |
Public Notice End Date |
Mar 24, 2015 |
Mail Agenda Notice |
Mar 24, 2015 |
Plans Received |
Mar 31, 2015 |
Biologist Report |
Apr 01, 2015 |
Supervisor Biologist SignOff |
Apr 02, 2015 |
Executive Signoff of Staff Reports |
Apr 07, 2015 |
Objections/Comments Received |
Apr 14, 2015 |
Semi-Monthly Meeting Date Scheduled |
Apr 14, 2015 |
Council Approval Granted |
Apr 17, 2015 |
Stipulation Package from Biologist |
Apr 21, 2015 |
Typist for Processing |
Apr 21, 2015 |
Executive Sign Off |
Apr 22, 2015 |
Permit Approved |
May 12, 2015 |
Legal Response/Decision |
Feb 01, 2016 |
Modification Request |
Feb 02, 2016 |
Administrative Review for Completeness |
Feb 05, 2016 |
Team Review for Completeness |
Feb 15, 2016 |
Biologist Report |
Feb 15, 2016 |
Typist for Processing |
Feb 18, 2016 |
Executive Sign Off |
Feb 18, 2016 |
Sent to Photo Copy |
Feb 18, 2016 |
Modification Approved |
Mar 11, 2016 |
Land Evidence Date |
Jan 23, 2017 |
Modification Request |
Jan 25, 2017 |
Administrative Review for Completeness |
Jan 26, 2017 |
Team Review for Completeness |
Jan 26, 2017 |
Deficient Application - Owner Notification Sent |
Jan 11, 2019 |
Deficient Application Discarded/No deficiency Reponse |
Feb 23, 2021 |
Modification Request |
Feb 25, 2021 |
Administrative Review for Completeness |
Mar 03, 2021 |
Bio Team Review for Completeness |
Mar 03, 2021 |
Deficient Application - Owner Notification Sent |
Aug 04, 2021 |
Deficiency Response Received |
Aug 10, 2021 |
Administrative Review for Completeness |
Aug 12, 2021 |
Bio Team Review for Completeness |
Aug 12, 2021 |
Project Manager |
Aug 18, 2021 |
30 day Public Notice Issued |
Aug 20, 2021 |
HPHC Historical Preservation No Effect |
Aug 20, 2021 |
HPHC Review Pending |
Sep 19, 2021 |
Public Notice End Date |
Sep 24, 2021 |
Public Notice End Date Extension Granted |
Sep 24, 2021 |
Comments Received |
Sep 24, 2021 |
Biologist Report |
Dec 14, 2021 |
Dock Meeting -- Approval |
Jan 13, 2022 |
Typist for Processing |
Jan 13, 2022 |
Modification Approved |
Jan 13, 2022 |
Stipulation Package from Biologist |
Jan 18, 2022 |
Permit Mailed |
Feb 10, 2022 |
Commencement of Work Notice received |