Action Date | Action Description |
---|---|
Mar 02, 2015 | Assent Application Received |
Mar 13, 2015 | Administrative Review for Completeness |
Mar 13, 2015 | Team Review for Completeness |
Mar 13, 2015 | Application Accepted |
Mar 18, 2015 | HPHC Historical Preservation No Effect |
Mar 27, 2015 | Biologist Report |
Mar 30, 2015 | Typist for Processing |
Mar 31, 2015 | Executive Sign Off |
Mar 31, 2015 | Sent to Photo Copy |
Mar 31, 2015 | Permit Approved |
Apr 27, 2015 | Land Evidence Date |
Jun 26, 2017 | Extension Toll letter mailed |
Apr 08, 2019 | Extension of Permit Request |
Apr 11, 2019 | Enforcement Compliance Inspection Required |
Apr 12, 2019 | Process Extension |
Apr 12, 2019 | Extension Approved |
Jun 17, 2020 | Extension of Permit Request |
Jun 26, 2020 | Enforcement Compliance Inspection Required |
Jun 29, 2020 | Process Extension |
Jun 29, 2020 | Extension Approved |
Jul 19, 2021 | Extension of Permit Request |
Mar 14, 2022 | Enforcement Compliance Inspection Required |
Mar 14, 2022 | Process Extension |
Mar 15, 2022 | Extension Approved |