Action Date | Action Description |
---|---|
May 19, 2015 | Assent Application Received |
May 22, 2015 | Administrative Review for Completeness |
May 26, 2015 | Team Review for Completeness |
May 26, 2015 | Application Accepted |
May 27, 2015 | Biologist Report |
Jun 04, 2015 | Additional Information Received |
Jun 12, 2015 | Typist for Processing |
Jun 12, 2015 | Permit Approved |
Jun 15, 2015 | Executive Sign Off |
Jun 15, 2015 | Sent to Photo Copy |
Jun 30, 2015 | HPHC Historical Preservation Comments/Concerns |