Action Date | Action Description |
---|---|
Jul 10, 2015 | Assent Application Received |
Jul 16, 2015 | Administrative Review for Completeness |
Jul 20, 2015 | Team Review for Completeness |
Jul 20, 2015 | Team Review for Completeness |
Jul 20, 2015 | Application Accepted |
Jul 20, 2015 | Engineering Report |
Jul 20, 2015 | Biologist Report |
Jul 24, 2015 | Typist for Processing |
Jul 27, 2015 | HPHC Historical Preservation No Effect |
Jul 29, 2015 | Sent to Photo Copy |
Jul 29, 2015 | Permit Approved |
Aug 04, 2015 | Land Evidence Date |
Jul 28, 2016 | Modification Request |
Jul 29, 2016 | Administrative Review for Completeness |
Aug 01, 2016 | Team Review for Completeness |
Aug 01, 2016 | Team Review for Completeness |
Aug 01, 2016 | Application Accepted |
Aug 17, 2016 | HPHC Historical Preservation No Effect |
Apr 04, 2017 | 30-Day Notification of Cancellation letter |
Apr 10, 2017 | Additional Information Received |
Apr 25, 2017 | Biologist Report |
Apr 26, 2017 | Engineering Report |
Apr 26, 2017 | Typist for Processing |
Apr 26, 2017 | Executive Sign Off |
Apr 26, 2017 | Sent to Photo Copy |
Apr 26, 2017 | Modification Approved |
May 09, 2017 | Land Evidence Date |
Jun 22, 2017 | Modification Request |
Jun 23, 2017 | Administrative Review for Completeness |
Jun 26, 2017 | Team Review for Completeness |
Jun 26, 2017 | Team Review for Completeness |
Jun 26, 2017 | Application Accepted |
Jul 19, 2017 | Engineering Report |
Jul 19, 2017 | Biologist Report |
Jul 19, 2017 | Typist for Processing |
Jul 19, 2017 | Executive Sign Off |
Jul 19, 2017 | Sent to Photo Copy |
Jul 19, 2017 | Modification Approved |
Dec 18, 2017 | HPHC Historical Preservation No Effect |