Action Date | Action Description |
---|---|
Oct 13, 2015 | Assent Application Received |
Oct 14, 2015 | Administrative Review for Completeness |
Oct 16, 2015 | Team Review for Completeness |
Oct 16, 2015 | Team Review for Completeness |
Oct 16, 2015 | Application Accepted |
Oct 30, 2015 | 30 day Public Notice Issued |
Nov 30, 2015 | Public Notice End Date |
Dec 04, 2015 | Additional Information Received |
Dec 29, 2015 | HPHC Historical Preservation No Effect |
Jan 06, 2016 | Permit Approved |
Jan 07, 2016 | Engineering Report |
Jan 07, 2016 | Sent to Photo Copy |
Jan 08, 2016 | Typist for Processing |
Jan 11, 2016 | Executive Sign Off |
Jan 11, 2016 | Biologist Report |
Jan 11, 2016 | Permit Approved |
Feb 08, 2016 | Land Evidence Date |