Action Date | Action Description |
---|---|
Dec 04, 2015 | Assent Application Received |
Dec 08, 2015 | Administrative Review for Completeness |
Dec 16, 2015 | Team Review for Completeness |
Dec 16, 2015 | Application Accepted |
Jan 04, 2016 | HPHC Historical Preservation No Effect |
Jan 08, 2016 | Engineering Report |
Jan 12, 2016 | Typist for Processing |
Jan 13, 2016 | Executive Sign Off |
Jan 13, 2016 | Sent to Photo Copy |
Jan 13, 2016 | Permit Approved |
Feb 12, 2016 | Duplicate Original Assent requested/mailed |
Feb 22, 2016 | Land Evidence Date |