Action Date | Action Description |
---|---|
Dec 24, 2015 | Assent Application Received |
Dec 31, 2015 | Administrative Review for Completeness |
Jan 05, 2016 | Team Review for Completeness |
Jan 12, 2016 | Deficient Application - Owner Notification Sent |
Jan 26, 2016 | Deficiency Response Received |
Jan 27, 2016 | Team Review for Completeness |
Jan 27, 2016 | Application Accepted |
Feb 02, 2016 | HPHC Historical Preservation No Effect |
Feb 17, 2016 | Additional Information Requested from Applicant |
Mar 03, 2016 | Additional Information Received |
Mar 03, 2016 | Plans Received |
Mar 10, 2016 | Biologist Report |
Mar 11, 2016 | Typist for Processing |
Mar 14, 2016 | Executive Sign Off |
Mar 14, 2016 | Sent to Photo Copy |
Mar 14, 2016 | Permit Approved |
Apr 21, 2016 | Land Evidence Date |
Dec 30, 2016 | Modification Request |
Jan 03, 2017 | Administrative Review for Completeness |
Jan 06, 2017 | Team Review for Completeness |
Jan 06, 2017 | Application Accepted |
Feb 03, 2017 | HPHC Historical Preservation No Effect |
Feb 16, 2017 | Biologist Report |
Feb 21, 2017 | Typist for Processing |
Feb 21, 2017 | Modification Approved |