Action Date | Action Description |
---|---|
Jan 27, 2016 | Assent Application Received |
Jan 27, 2016 | Administrative Review for Completeness |
Jan 29, 2016 | Team Review for Completeness |
Jan 29, 2016 | Application Accepted |
Feb 02, 2016 | HPHC Historical Preservation No Effect |
Mar 30, 2016 | Plans Received |
Apr 13, 2016 | Plans Received |
Apr 15, 2016 | Engineering Report |
Apr 18, 2016 | Typist for Processing |
Apr 20, 2016 | Executive Sign Off |
Apr 20, 2016 | Sent to Photo Copy |
Apr 20, 2016 | Permit Approved |
May 20, 2016 | Land Evidence Date |
Apr 17, 2017 | RIPDES Permit Issued |