Action Date | Action Description |
---|---|
HPHC Historical Preservation No Effect | |
Mar 24, 2016 | Assent Application Received |
Mar 25, 2016 | Administrative Review for Completeness |
Apr 15, 2016 | Team Review for Completeness |
Apr 15, 2016 | Application Accepted |
Apr 28, 2016 | 30 day Public Notice Issued |
May 26, 2016 | US Army Corps of Engineers Approval Received |
May 28, 2016 | Public Notice End Date |
Aug 03, 2016 | Dock Meeting Scheduled (Admin) |
Aug 03, 2016 | Dock Meeting -- Approval |
Aug 03, 2016 | Category A* (Docks) |
Aug 05, 2016 | Biologist Report |
Aug 05, 2016 | Engineering Report |
Aug 09, 2016 | Typist for Processing |
Aug 10, 2016 | Executive Sign Off |
Aug 10, 2016 | Sent to Photo Copy |
Aug 10, 2016 | Permit Approved |
Aug 23, 2016 | Land Evidence Date |