Action Date | Action Description |
---|---|
Sep 21, 2016 | Assent Application Received |
Sep 21, 2016 | Administrative Review for Completeness |
Sep 29, 2016 | Team Review for Completeness |
Oct 05, 2016 | Application Accepted |
Oct 05, 2016 | Team Review for Completeness |
Oct 25, 2016 | HPHC Historical Preservation No Effect |
Oct 31, 2016 | Engineering Report |
Nov 01, 2016 | Typist for Processing |
Nov 01, 2016 | Executive Sign Off |
Nov 01, 2016 | Sent to Photo Copy |
Nov 01, 2016 | Permit Approved |