Action Date | Action Description |
---|---|
Apr 28, 2017 | Maintenance Certification Request |
May 02, 2017 | Administrative Review for Completeness |
May 11, 2017 | Team Review for Completeness |
May 16, 2017 | Typist for Processing |
May 16, 2017 | Executive Sign Off |
May 16, 2017 | Sent to Photo Copy |
May 16, 2017 | Application Accepted |
May 16, 2017 | Permit Approved |
Apr 02, 2018 | Commencement of Work Notice received |