Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Nov 06, 2017 | Assent Application Received |
Nov 06, 2017 | Administrative Review for Completeness |
Nov 07, 2017 | Team Review for Completeness |
Nov 07, 2017 | Application Accepted |
Nov 07, 2017 | Category A* (Docks) |
Dec 01, 2017 | 30 day Public Notice Issued |
Jan 01, 2018 | Public Notice End Date |
Feb 21, 2018 | Additional Information Received |
Apr 05, 2018 | Objections/Comments Received |
Jun 18, 2018 | Additional Information Received |
Jun 21, 2018 | HPHC Historical Preservation No Effect |
Jul 06, 2018 | Engineering Report |
Jul 09, 2018 | Permit Approved |
Jul 09, 2018 | Typist for Processing |
Jul 09, 2018 | Executive Sign Off |
Jul 09, 2018 | Sent to Photo Copy |
Aug 01, 2018 | Land Evidence Date |