Action Date | Action Description |
---|---|
Feb 20, 2018 | Assent Application Received |
Feb 20, 2018 | Administrative Review for Completeness |
Feb 27, 2018 | Team Review for Completeness |
Feb 27, 2018 | Application Accepted |
Mar 20, 2018 | Additional Information Requested from Applicant |
Apr 11, 2018 | HPHC Historical Preservation Comments/Concerns |
Jun 08, 2018 | Plans Received |
Aug 16, 2018 | Plans Received |
Oct 15, 2018 | HPHC Historical Preservation No Effect |
Oct 26, 2018 | Permit Approved |
Oct 26, 2018 | Typist for Processing |
Oct 26, 2018 | Sent to Photo Copy |
Oct 26, 2018 | Biologist Report |
Oct 26, 2018 | Engineering Report |
Jan 23, 2019 | Land Evidence Date |