Action Date | Action Description |
---|---|
Aug 10, 2018 | Assent Application Received |
Aug 13, 2018 | Administrative Review for Completeness |
Aug 14, 2018 | Team Review for Completeness |
Aug 14, 2018 | Application Accepted |
Aug 21, 2018 | Additional Information Requested from Applicant |
Aug 27, 2018 | HPHC Historical Preservation No Effect |
Sep 10, 2018 | Note to File |
Sep 12, 2018 | Additional Information Received |
Sep 14, 2018 | Additional Information Received |
Oct 03, 2018 | 30-Day Notification of Cancellation letter |
Oct 03, 2018 | Note to File |
Oct 09, 2018 | Additional Information Received |
Nov 01, 2018 | Plans Received |
Nov 27, 2018 | Typist for Processing |
Nov 27, 2018 | Executive Sign Off |
Nov 27, 2018 | Sent to Photo Copy |
Nov 27, 2018 | Permit Approved |
Nov 27, 2018 | Biologist Report |
Jan 04, 2019 | Land Evidence Date |