Action Date | Action Description |
---|---|
Feb 07, 2020 | Assent Application Received |
Feb 10, 2020 | Administrative Review for Completeness |
Feb 19, 2020 | Team Review for Completeness |
Feb 19, 2020 | Application Accepted |
Feb 25, 2020 | HPHC Review Pending |
Feb 25, 2020 | HPHC Historical Preservation No Effect |
Mar 06, 2020 | Project Manager |
Mar 20, 2023 | 30-Day Notification of Cancellation letter |
Nov 13, 2024 | Additional Information Received |
Nov 13, 2024 | Biologist Report |