Action Date | Action Description |
---|---|
Feb 10, 2020 | Assent Application Received |
Feb 10, 2020 | Administrative Review for Completeness |
Feb 11, 2020 | Bio Team Review for Completeness |
Feb 11, 2020 | Application Accepted |
Feb 25, 2020 | HPHC Review Pending |
Feb 25, 2020 | HPHC Historical Preservation No Effect |
Mar 03, 2020 | Additional Information Received |
Mar 04, 2020 | Biologist Report |
Mar 05, 2020 | Typist for Processing |
Mar 05, 2020 | Executive Sign Off |
Mar 05, 2020 | Sent to Photo Copy |
Mar 05, 2020 | Permit Approved |
Mar 06, 2020 | Land Evidence Date |