Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Nov 09, 2020 | Assent Application Received |
Nov 10, 2020 | Administrative Review for Completeness |
Nov 24, 2020 | Eng Team Review for Completeness |
Nov 24, 2020 | Application Accepted |
Nov 24, 2020 | Project Manager |
Nov 25, 2020 | Category A* (Docks) |
Dec 07, 2020 | 30 day Public Notice Issued |
Dec 23, 2020 | HPHC Review Pending |
Dec 23, 2020 | HPHC Historical Preservation No Effect |
Jan 06, 2021 | Objections/Comments Received |
Jan 07, 2021 | Public Notice End Date |
Feb 02, 2021 | Comments Received |
Mar 29, 2021 | Correspondence Received |
Apr 16, 2021 | Plans Received |
May 03, 2021 | Additional Information Requested from Applicant |
Jun 03, 2021 | Objections/Comments Received |
Jun 18, 2021 | Additional Information Received |
Jul 09, 2021 | 30 day Public Notice Issued |
Aug 06, 2021 | Objections/Comments Received |
Aug 09, 2021 | Public Notice End Date |
Aug 25, 2021 | Entry of Appearance Received |
Nov 01, 2021 | Plans Received |
Nov 08, 2021 | Engineering Report |
Nov 12, 2021 | Executive Signoff of Staff Reports |
Jan 14, 2022 | Ready to Schedule Semi-Monthly Meeting |
Jan 14, 2022 | Mail Agenda Notice |
Jan 25, 2022 | Council Approval Granted |
Jan 25, 2022 | Semi-Monthly Meeting Date Scheduled |
Mar 23, 2022 | Legal Response/Decision |
Apr 28, 2022 | Stipulation Package by Engineer |
Apr 29, 2022 | Typist for Processing |
Apr 29, 2022 | Permit Mailed |
Apr 29, 2022 | Permit Approved |
May 02, 2022 | Permit Mailed |
Aug 08, 2022 | Land Evidence Date |