Action Date | Action Description |
---|---|
Apr 23, 2021 | Assent Application Received |
Apr 23, 2021 | Administrative Review for Completeness |
Apr 26, 2021 | Eng Team Review for Completeness |
Apr 26, 2021 | Application Accepted |
May 17, 2021 | HPHC Historical Preservation No Effect |
May 17, 2021 | HPHC Review Pending |
Jun 18, 2021 | Stipulation Package by Engineer |
Jun 18, 2021 | Project Manager |
Jun 18, 2021 | Engineering Report |
Jun 23, 2021 | Typist for Processing |
Jun 23, 2021 | Executive Sign Off |
Jun 23, 2021 | Sent to Photo Copy |
Jun 23, 2021 | Permit Approved |
Aug 19, 2021 | Land Evidence Date |