Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Aug 10, 2021 | Assent Application Received |
Aug 12, 2021 | Administrative Review for Completeness |
Aug 17, 2021 | Bio Team Review for Completeness |
Aug 17, 2021 | Application Accepted |
Aug 17, 2021 | Project Manager |
Aug 17, 2021 | Category A* (Docks) |
Aug 20, 2021 | HPHC Review Pending |
Aug 20, 2021 | HPHC Historical Preservation No Effect |
Oct 14, 2021 | Dock Meeting -- Approval |
Oct 22, 2021 | Biologist Report |
Nov 01, 2021 | Typist for Processing |
Nov 01, 2021 | Permit Approved |
Nov 02, 2021 | Permit Mailed |
Nov 02, 2021 | Executive Sign Off |
Jan 10, 2022 | Land Evidence Date |