Action Date | Action Description |
---|---|
Oct 28, 2021 | Assent Application Received |
Nov 01, 2021 | Administrative Review for Completeness |
Nov 01, 2021 | CHA Worksheet received |
Nov 16, 2021 | Bio Team Review for Completeness |
Nov 16, 2021 | Application Accepted |
Nov 17, 2021 | Project Manager |
Jan 11, 2022 | 30 day Public Notice Issued |
Jan 18, 2022 | Objections/Comments Received |
Jan 18, 2022 | Note to File |
Jan 24, 2022 | HPHC Historical Preservation No Effect |
Jan 24, 2022 | HPHC Review Pending |
Jan 31, 2022 | Objections/Comments Received |
Feb 09, 2022 | Comments Received |
Feb 10, 2022 | Objections/Comments Received |
Feb 11, 2022 | Objections/Comments Received |
Feb 11, 2022 | Public Notice End Date |
Mar 07, 2022 | Additional Information Requested from Applicant |
Mar 17, 2022 | Objections/Comments Received |
Mar 23, 2022 | Additional Information Received |
Apr 07, 2022 | Additional Information Received |
Jul 15, 2022 | Additional Information Received |
Aug 19, 2022 | Additional Information Received |
Oct 05, 2022 | Conservation Easement and Restrictions Requested |
Oct 31, 2022 | Conservation Easement and Restrictions Requested |
Feb 20, 2023 | Additional Information Received |
Mar 09, 2023 | Mail Agenda Notice |
Mar 16, 2023 | Biologist Report |
Mar 16, 2023 | Engineering Report |
Mar 28, 2023 | Continued application |
Mar 28, 2023 | Semi-Monthly Meeting Date Scheduled |
Apr 04, 2023 | Mail Agenda Notice |
Apr 24, 2023 | Council Approval Granted |
Apr 24, 2023 | Semi-Monthly Meeting Date Scheduled |
May 11, 2023 | Additional Information Received |
Jul 06, 2023 | Additional Information Received |
Jul 10, 2023 | Legal Response/Decision |
Jul 19, 2023 | Stipulation Package from Biologist |
Jul 21, 2023 | Stipulation Package by Engineer |
Jul 24, 2023 | Permit Mailed |
Jul 25, 2023 | Typist for Processing |
Jul 27, 2023 | Executive Sign Off |
Jul 27, 2023 | Sent to Photo Copy |
Jul 27, 2023 | Permit Approved |
Aug 04, 2023 | Land Evidence Date |
Apr 01, 2024 | Assent Requirement |