Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Jan 05, 2023 | Assent Application Received |
Jan 10, 2023 | Administrative Review for Completeness |
Jan 11, 2023 | Bio Team Review for Completeness |
Jan 11, 2023 | Project Manager |
Jan 11, 2023 | Application Accepted |
Jan 17, 2023 | HPHC Historical Preservation No Effect |
Feb 21, 2023 | 30 day Public Notice Issued |
Mar 17, 2023 | Objections/Comments Received |
Mar 23, 2023 | Public Notice End Date |
Aug 25, 2023 | Comments Received |
Aug 29, 2023 | Biologist Report |
Sep 06, 2023 | Mail Agenda Notice |
Sep 07, 2023 | Continuance Requested |
Sep 07, 2023 | Supervisor Biologist SignOff |
Sep 07, 2023 | Supervisor Engineer SignOff |
Sep 07, 2023 | Executive Signoff of Staff Reports |
Sep 11, 2023 | Continuance request by objector granted by Director |
Sep 12, 2023 | Semi-Monthly Meeting Date Scheduled |
Sep 14, 2023 | Mail Agenda Notice |
Sep 20, 2023 | Continuance Requested |
Sep 20, 2023 | Continuance Requested by Objector Denied |
Sep 26, 2023 | Council Approval Granted |
Sep 26, 2023 | Semi-Monthly Meeting Date Scheduled |
Feb 02, 2024 | Stipulation Package from Biologist |
Jul 09, 2024 | Legal Response/Decision |
Sep 11, 2024 | Typist for Processing |
Sep 11, 2024 | Executive Sign Off |
Sep 11, 2024 | Sent to Photo Copy |
Sep 11, 2024 | Permit Approved |
Sep 16, 2024 | Permit Mailed |
Sep 24, 2024 | Land Evidence Date |