Action Date | Action Description |
---|---|
Mar 17, 2023 | Preliminary Determination Request (Coastal) |
Mar 21, 2023 | Administrative Review for Completeness |
Mar 23, 2023 | Bio Team Review for Completeness |
Mar 23, 2023 | Application Accepted |
Mar 23, 2023 | Project Manager |
Apr 11, 2023 | HPHC Historical Preservation No Effect |
May 17, 2023 | Assent Application Received |
May 17, 2023 | CHA Worksheet received |
Aug 04, 2023 | Biologist Report |
Aug 07, 2023 | Typist for Processing |
Aug 07, 2023 | Executive Sign Off |
Aug 07, 2023 | Sent to Photo Copy |
Aug 07, 2023 | Permit Approved |
Aug 09, 2023 | Permit Mailed |
Sep 19, 2023 | Land Evidence Date |
May 31, 2024 | Modification Request |
Jun 07, 2024 | Administrative Review for Completeness |
Jun 10, 2024 | Bio Team Review for Completeness |
Jun 10, 2024 | Project Manager |
Jun 10, 2024 | Application Accepted |
Jul 01, 2024 | HPHC Historical Preservation No Effect |
Jul 31, 2024 | Biologist Report |
Aug 01, 2024 | Modification Approved |
Aug 05, 2024 | Modification mailed |
Aug 26, 2024 | Land Evidence Date |
Sep 10, 2024 | Commencement of Work Notice received |