Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Mar 27, 2023 | Assent Application Received |
Mar 29, 2023 | Administrative Review for Completeness |
Mar 31, 2023 | Bio Team Review for Completeness |
Mar 31, 2023 | Application Accepted |
Mar 31, 2023 | Project Manager |
Apr 11, 2023 | HPHC Historical Preservation No Effect |
Apr 27, 2023 | Plans Received |
May 16, 2023 | 30 day Public Notice Issued |
Jun 16, 2023 | Public Notice End Date |
Aug 01, 2023 | Dock/1.1.6 Review approval |
Aug 01, 2023 | Biologist Report |
Aug 08, 2023 | Typist for Processing |
Aug 08, 2023 | Executive Sign Off |
Aug 08, 2023 | Sent to Photo Copy |
Aug 08, 2023 | Permit Approved |
Aug 09, 2023 | Permit Mailed |
Aug 25, 2023 | Land Evidence Date |
Mar 13, 2024 | Commencement of Work Notice received |