Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Land Evidence Date | |
Jan 22, 2024 | Assent Application Received |
Jan 29, 2024 | Administrative Review for Completeness |
Mar 25, 2024 | Bio Team Review for Completeness |
Mar 25, 2024 | Project Manager |
Mar 25, 2024 | Application Accepted |
Mar 25, 2024 | Category A* (Docks) |
Mar 29, 2024 | HPHC Historical Preservation No Effect |
Jun 03, 2024 | 30 day Public Notice Issued |
Jul 03, 2024 | Public Notice End Date |
Jul 10, 2024 | Dock/1.1.6 Review approval |
Jul 31, 2024 | Plans Received |
Aug 28, 2024 | Biologist Report |
Aug 29, 2024 | Typist for Processing |
Aug 29, 2024 | Executive Sign Off |
Aug 29, 2024 | Sent to Photo Copy |
Aug 29, 2024 | Permit Approved |
Sep 03, 2024 | Permit Mailed |