Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Dec 16, 1994 | Application Accepted |
Apr 05, 1995 | Engineering Report |
Apr 06, 1995 | Permit Approved |
Apr 06, 1995 | Land Evidence Date |
Nov 20, 2018 | Modification Request |
Nov 20, 2018 | Administrative Review for Completeness |
Nov 26, 2018 | Team Review for Completeness |
Dec 21, 2018 | Deficient Application - Owner Notification Sent |
Jan 24, 2019 | Deficiency Response Received |
Jan 28, 2019 | Team Review for Completeness |
Jan 28, 2019 | Application Accepted |
Feb 20, 2019 | HPHC Historical Preservation No Effect |
Feb 25, 2019 | 30 day Public Notice Issued |
Mar 25, 2019 | Public Notice End Date |
Apr 05, 2019 | Dock/1.1.6 Review approval |
Apr 10, 2019 | Engineering Report |
Apr 11, 2019 | Typist for Processing |
Apr 11, 2019 | Executive Sign Off |
Apr 11, 2019 | Sent to Photo Copy |
Apr 11, 2019 | Permit Approved |
May 10, 2019 | Land Evidence Date |