Action Date | Action Description |
---|---|
Jan 13, 1997 | ISDS Approved |
Mar 12, 2001 | Application Accepted |
Sep 24, 2001 | Engineering Report |
Sep 25, 2001 | Biologist Report |
Sep 25, 2001 | Permit Approved |
Sep 25, 2001 | Land Evidence Date |
Jul 09, 2003 | Modification Request |
Jul 22, 2003 | Historical Preservation Approval Granted |
Sep 30, 2003 | Biologist Report |
Sep 30, 2003 | Engineering Report |
Oct 10, 2003 | Modification Approved |
Sep 25, 2004 | Extension Approved |
May 17, 2005 | Extension of Permit Request |
Jun 10, 2005 | Enforcement Compliance Inspection Required |
Jun 10, 2005 | Process Extension |
Jun 21, 2005 | Ready to Schedule Semi-Monthly Meeting |
Jun 21, 2005 | Mail Agenda Notice |
Jun 28, 2005 | Correspondence Received |
Jun 28, 2005 | Semi-Monthly Meeting Held |
Jun 28, 2005 | Council Approval Granted |
Jun 28, 2005 | Semi-Monthly Meeting Date Scheduled |
Jul 01, 2005 | Extension Approved |
Jul 06, 2005 | Executive Sign Off |
Jul 06, 2005 | Sent to Photo Copy |
Jul 06, 2005 | Typist for Processing |