Action Date | Action Description |
---|---|
Jan 05, 2004 | Application Accepted |
Jan 12, 2004 | Engineering Report |
Jan 26, 2004 | Permit Approved |
Jan 26, 2004 | Land Evidence Date |
Aug 10, 2006 | Modification Request |
Aug 15, 2006 | Administrative Review for Completeness |
Aug 24, 2006 | Deficient Application - Owner Notification Sent |
Aug 24, 2006 | Deficient Application Picked Up |
Oct 03, 2006 | Deficiency Response Received |
Oct 06, 2006 | Team Review for Completeness |
Oct 19, 2006 | HPHC Historical Preservation No Effect |
Oct 25, 2006 | 30 day Public Notice Issued |
Nov 25, 2006 | Public Notice End Date |
Dec 27, 2006 | US Army Corp of Engineers Permit Date |
Dec 29, 2006 | US Army Corps of Engineers Approval Received |
Feb 09, 2007 | Biologist Report |
Feb 09, 2007 | Engineering Report |
Feb 13, 2007 | Typist for Processing |
Feb 13, 2007 | Executive Sign Off |
Feb 13, 2007 | Sent to Photo Copy |
Feb 13, 2007 | Modification Approved |
Mar 01, 2007 | Land Evidence Date |
Aug 01, 2007 | Commencement of Work Notice received |