Action Date | Action Description |
---|---|
Jan 31, 2005 | Assent Application Received |
Feb 18, 2005 | Administrative Review for Completeness |
Mar 07, 2005 | Deficient Application - Owner Notification Sent |
Jul 07, 2005 | Deficiency Response Received |
Jul 12, 2005 | Team Review for Completeness |
Jul 20, 2005 | Deficient Application - Owner Notification Sent |
Aug 09, 2005 | Deficient Application Picked Up |
Feb 01, 2006 | Deficiency Response Received |
Feb 10, 2006 | Team Review for Completeness |
Feb 10, 2006 | Application Accepted |
Feb 10, 2006 | Category B assigned |
Mar 03, 2006 | HPHC Historical Preservation No Effect |
Mar 14, 2006 | 30 day Public Notice Issued |
Apr 14, 2006 | Public Notice End Date |
Apr 19, 2006 | Objections/Comments Received |
May 22, 2006 | US Army Corp of Engineers Permit Date |
May 23, 2006 | Engineering Report |
May 24, 2006 | Executive Sign Off |
May 25, 2006 | US Army Corps of Engineers Approval Received |
Jun 15, 2006 | Ready to Schedule Semi-Monthly Meeting |
Jun 15, 2006 | Mail Agenda Notice |
Jun 27, 2006 | Semi-Monthly Meeting Held |
Jun 27, 2006 | Council Approval Granted |
Jun 27, 2006 | Semi-Monthly Meeting Date Scheduled |
Jul 11, 2006 | Typist for Processing |
Jul 11, 2006 | Executive Sign Off |
Jul 11, 2006 | Sent to Photo Copy |
Jul 11, 2006 | Permit Approved |
Jul 11, 2006 | Stipulation Package from Biologist |
Jul 11, 2006 | Stipulation Package by Engineer |
Jul 21, 2006 | Land Evidence Date |
Aug 24, 2006 | Legal Response/Decision |