Action Date | Action Description |
---|---|
Apr 13, 2005 | Assent Application Received |
Apr 14, 2005 | Administrative Review for Completeness |
Apr 14, 2005 | Team Review for Completeness |
Apr 14, 2005 | Application Accepted |
Apr 15, 2005 | Category B assigned |
May 03, 2005 | HPHC Review Pending |
May 16, 2005 | Biologist Report |
May 16, 2005 | Engineering Report |
May 16, 2005 | 30 day Public Notice Issued |
May 16, 2005 | Executive Sign Off |
May 26, 2005 | Supervisor Biologist SignOff |
May 26, 2005 | Supervisor Engineer SignOff |
Jun 02, 2005 | Executive Sign Off |
Jun 02, 2005 | Mail Agenda Notice |
Jun 14, 2005 | Semi-Monthly Meeting Date Scheduled |
Jun 14, 2005 | Correspondence Received |
Jun 14, 2005 | Correspondence Received |
Jun 14, 2005 | Council Approval Granted |
Jun 16, 2005 | Public Notice End Date |
Jul 08, 2005 | Correspondence Received |
Sep 16, 2005 | Biologist Report |
Sep 16, 2005 | Typist for Processing |
Sep 16, 2005 | Permit Approved |
Sep 16, 2005 | Stipulation Package from Biologist |
Sep 16, 2005 | Stipulation Package by Engineer |
Sep 19, 2005 | Legal Response/Decision |
Sep 19, 2005 | Executive Sign Off |
Sep 19, 2005 | Sent to Photo Copy |
Sep 29, 2005 | Land Evidence Date |
Apr 24, 2009 | Correspondence Mailed/Faxed/E-mailed |
Aug 05, 2009 | Conservation Easement Mailed. |
Aug 19, 2009 | Conservation Easement Recording received |