Action Date | Action Description |
---|---|
Jun 07, 2005 | Assent Application Received |
Jun 08, 2005 | Administrative Review for Completeness |
Jun 08, 2005 | Team Review for Completeness |
Jun 08, 2005 | Application Accepted |
Jun 15, 2005 | 30 day Public Notice Issued |
Jun 27, 2005 | Historical Preservation Approval Granted |
Jul 15, 2005 | Public Notice End Date |
Jul 18, 2005 | US Army Corp of Engineers Permit Date |
Jul 20, 2005 | US Army Corps of Engineers Approval Received |
Jul 29, 2005 | Engineering Report |
Jul 29, 2005 | Biologist Report |
Aug 01, 2005 | Typist for Processing |
Aug 01, 2005 | Executive Sign Off |
Aug 01, 2005 | Sent to Photo Copy |
Aug 01, 2005 | Permit Approved |
Aug 24, 2005 | Land Evidence Date |
Jun 05, 2006 | Commencement of Work Notice received |
Feb 23, 2007 | Modification Request |
Feb 23, 2007 | Administrative Review for Completeness |
Feb 26, 2007 | Team Review for Completeness |
Feb 26, 2007 | Team Review for Completeness |
Feb 28, 2007 | 30 day Public Notice Issued |
Mar 05, 2007 | HPHC Historical Preservation No Effect |
Mar 08, 2007 | Category A* (Docks) |
Mar 27, 2007 | US Army Corp of Engineers Permit Date |
Mar 28, 2007 | US Army Corps of Engineers Approval Received |
Mar 30, 2007 | Public Notice End Date |
Apr 13, 2007 | Biologist Report |
Apr 13, 2007 | Engineering Report |
Apr 16, 2007 | Typist for Processing |
Apr 16, 2007 | Executive Sign Off |
Apr 16, 2007 | Sent to Photo Copy |
Apr 16, 2007 | Modification Approved |
Jun 28, 2007 | Land Evidence Date |