Action Date | Action Description |
---|---|
Jun 24, 2005 | Assent Application Received |
Jun 27, 2005 | Administrative Review for Completeness |
Jun 28, 2005 | Team Review for Completeness |
Jun 28, 2005 | Application Accepted |
Jul 14, 2005 | HPHC Review Pending |
Sep 14, 2005 | Biologist Report |
Sep 14, 2005 | Engineering Report |
Sep 15, 2005 | Typist for Processing |
Sep 16, 2005 | Executive Sign Off |
Sep 16, 2005 | Sent to Photo Copy |
Sep 16, 2005 | Permit Approved |
Oct 14, 2005 | Land Evidence Date |
May 09, 2008 | Extension of Permit Request |
Jun 02, 2008 | Enforcement Compliance Inspection Required |
Jun 04, 2008 | Process Extension |
Jun 04, 2008 | Extension Approved |
Aug 07, 2009 | Extension of Permit Request |
Oct 13, 2009 | Enforcement Compliance Inspection Required |
Oct 13, 2009 | Process Extension |
Oct 13, 2009 | Extension Approved |
Jul 12, 2010 | Extension of Permit Request |
Oct 07, 2010 | Extension Toll letter mailed |
Mar 22, 2012 | Extension Toll letter mailed |